Curtain track in with the build, ready for drapes

22 curves, 118 brackets and more than 30 lengths of Triple E Erail, set into the ceiling of Lifepointe Baptist Church's new auditorium in Buderim while the builder was still on site. The track will carry the curtains that divide the room into three, and when the room is finished they go straight onto track that is already there.

Location
Buderim, Sunshine Coast
Years
2026
TSA Teams
Curtain Track · Installation · Drapes
Scroll
At a glance
01 Client

Lifepointe Baptist Church

02 Challenge

BADGE Constructions needed track for divider curtains built into a new church auditorium that splits into three rooms, following curved bulkheads 5.5 m up, before the ceiling closed in.

03 What we did

Triple E Erail with 13 custom bends and 9 stock curves, supplied and installed by our team in August 2026 on 118 brackets fixed to the ceiling substrate.

04 Outcome

Every run is in, level and parked out of sight, ready for the church to hang drapes when the room is handed over.

01 The Problem

Track is easiest to fit before the room is finished.

Lifepointe Baptist Church in Buderim lost its main auditorium to a fire in January 2023. The new building, now going up with BADGE Constructions, includes an auditorium designed to split into three rooms for weekday use.

Divider curtains turn one big room into three, and they are only as good as the track they run on. In a room like this the track belongs in the ceiling, not hung off it. The fixings go to the structure and the substrate while the ceiling is still open, the runs sit inside bulkheads and storage pockets, and the corners follow the architecture. Fit it after the finishes close and every bracket is a hole through a new ceiling.

So the track went in with the build, and the drapes follow once the room is handed over.

The new Lifepointe Church auditorium during fit-out, looking towards the stage under blue light, with the curtain track running along the ceiling bulkhead overhead. Photo: TSA.
Track in the ceiling bulkhead, fitted while the auditorium was still a build site.
02 The Process

Fixed to the structure, bent to the bulkhead, level end to end.

i
Looking straight up into a curtain storage pocket in the ceiling, with the support framing above and the parallel track runs leaving the pocket. Photo: TSA.

Brackets to the substrate, runs out of the pocket

Our team started at the storage pockets. The parallel runs leave each pocket and turn out into the auditorium, so the divider curtains can park out of sight when the auditorium is open as one room.

The straight runs fix to the ceiling substrate, and the breakout mounts on C-channel were drilled, installed and levelled before any track went up. The auditorium steel sits at 5.5 m.

ii
Erail curtain track fixed with a galvanised bracket inside the slot between two ceiling bulkheads, with the auditorium roof steel beyond. Photo: TSA.

118 brackets, set into the ceiling line

The runs hang on 118 suspension brackets: 58 straight and 60 flush. The flush brackets let the track sit tight inside the slot in the bulkhead, so from the floor it reads as a clean black line along the ceiling edge.

More than 30 six-metre lengths of Erail joined into the runs, with end stops on each.

iii
Three parallel runs of black Erail curtain track turning a rounded corner of the white ceiling bulkhead in the Lifepointe Church auditorium. Photo: TSA.

Bent to follow the room

The bulkheads turn corners, so the track does too. Alongside nine stock 750 mm curves, TSA bent 13 custom curves to the drawings: one at 650 mm radius, nine at 750 mm and three at 850 mm, each with straight tails to joint into the runs.

Erail can be curved down to 500 mm radius, so the track follows the bulkhead rather than the bulkhead being changed to suit the track.

03 The Result

The track is in. The drapes come next.

Our team finished the install in August 2026, with every run in, level and parked in its pocket. The builder closes the room around track that is already there.

Erail carries curtains up to 8 m tall, walkalong today, with corded or motorised drive available later on the same track. When the auditorium is handed over, the divider curtains are measured to the finished room and hung on the first visit, and the church can close the room into three spaces for weekday use.

Teams on this job

Engineered, installed, supported.
Under one roof.

Talk to us

Got a project that has to land first time?

Building or rebuilding an auditorium? Bring us in while the ceiling is open and the track goes in with the build, ready for drapes on handover. Straight answers, no hard sell.